South San Francisco Bay Shoreline Project
PROJECT BACKGROUND
This project will construct approximately 1.6 miles of flood risk management levees with approximately 600,000 cubic yards of fill to provide flood protection to homes, businesses, schools, streets, and highways by improving shoreline resilience against projected sea level rise, restoring a tidal marsh habitat, and connecting the area to a regional trail system.
PROJECT DETAILS:
Added Value: Our USACE accredited on-site mobile laboratory allows the G3 project team to provide seamless coordination of test results with field operations, ensuring that this complex construction project moves forward with actionable data to maintain project quality and eliminate costly rework.
Type: Water – Wastewater
Owner: US Army Corps of Engineers
Location: South San Francisco
G3 Quality’s Role
G3 is currently providing field and laboratory services for the soils testing utilizing our experienced technical staff and fully accredited on-site laboratory. In addition to the future scope of aggregate base and marine concrete, G3 is responsible for ensuring earthwork production and construction operations comply with the stringent contract requirements to produce a successful completed project.
PARTNER WITH US
Let us provide quality support and expertise for your next project.
Project Details
Name:
San Bernardino County Transportation Authority Interstate 10 Express Lanes Corridor Contract 1
Contract Number:
SBCTA 17-1001599; Lane Job #9151; G3 Project Number RD300
Value:
G3 Contract $9.5 million; Overall contract $673M
Type:
Design-Build
Client:
Lane – Security Paving Joint Venture
Owner:
San Bernardino County Transportation Authority
Location:
Los Angeles/San Bernardino County Line to the I-10/I-15 Interchange in Ontario.
Duration:
2019 to 2023